Most small garment units quote a price from memory and find out at the end of the order whether they made money. A garment costing sheet turns that guess into a calculation you can check before you say yes. Here is what goes on the sheet, a worked example, and the costs small units most often forget.

Why Quoting From Memory Loses Money
A buyer asks for a price on 500 kurtis. The owner remembers that the last similar order went at a certain rate, adds a little for rising cloth prices, and quotes. Sometimes the order makes money. Sometimes the fabric consumption was higher, the rejection rate was worse, or the karigars took longer on the new neck style, and the unit worked for a month for almost nothing.
The problem is not that the owner is careless. It is that a garment price is the sum of eight or nine separate costs, and memory only holds the two or three biggest ones. The small ones, thread, labels, packing, the cloth lost at the cutting table, the pieces that come back from checking, are each too small to remember and together large enough to eat the margin.
A costing sheet is one page per style that lists every cost, per piece, before the order is accepted. It takes twenty minutes to fill the first time and five minutes for every repeat style after that.
What Goes on the Sheet
Every cost is worked out per finished, saleable piece. That last word matters, because the pieces you cut and the pieces you sell are not the same number.
| Cost head | How to work it out per piece | What gets missed |
|---|
Fabric | Consumption per piece in metres, times price per metre | Cutting wastage and shrinkage allowance |
Lining and interlining | Same method as the main fabric | Left out on styles where only part is lined |
Trims | Buttons, zips, hooks, lace, elastic, counted per piece | Spares the karigars use and do not return |
Thread | Cones used per order, divided by pieces | Treated as free because it is cheap |
Labels and tags | Brand label, size label, wash care label, price tag | The wash care label, which buyers often require |
Cutting and stitching labour | Piece rate per garment, or daily wage divided by output | Helpers, checkers and the ironing man |
Finishing and packing | Pressing, folding, poly bag, carton share | The carton, which is paid per order, not per piece |
Overheads | Monthly rent, power and salaries, divided by monthly output | Left out entirely on rush orders |
Rejections | Expected rejected pieces, spread across the good ones | Assumed to be zero |
A Worked Example
Here is a simple cotton kurti, 500 pieces. The figures are an example of the method, not a price list; use your own rates.
| Cost head | Working | Per piece |
|---|
Fabric | 2.3 m at Rs 90 a metre | Rs 207 |
Trims | Buttons, piping | Rs 12 |
Thread | Cones for the order, divided by 500 | Rs 4 |
Labels and tags | Size, wash care, brand | Rs 6 |
Cutting and stitching | Piece rate including cutting | Rs 55 |
Finishing and packing | Pressing, poly bag, carton share | Rs 10 |
Overheads | Monthly fixed cost divided by monthly pieces | Rs 25 |
Subtotal | | Rs 319 |
Rejections | 1 in 40 pieces, so add one fortieth | Rs 8 |
Cost per saleable piece | | Rs 327 |
Only now do you set the price. Add your margin on the cost per saleable piece, then check the result against what the buyer has said they can pay. If the two are far apart, you know exactly which line to discuss, fabric, trims or labour, instead of cutting your margin blind.
Fabric Consumption: Measure It, Do Not Guess
Fabric is usually more than half the cost of a garment, so a small error here outweighs every other line on the sheet. An extra fifteen centimetres per kurti on a 500-piece order is 75 metres of cloth you paid for and did not price.
Find the real consumption by doing a marker. Lay out the pattern pieces for a full size set on the fabric width you will actually buy, as tightly as they will go, and measure the length used. Divide by the number of pieces in the set. That is your consumption per piece, and it already includes the gaps between pieces.
Then add the allowances: shrinkage if the fabric will be washed, a small extra for end losses and faults, and the matching allowance if it is a check or a stripe. Our guide on cutting fabric wastage shows how to tighten the marker, and how much cloth each garment needs gives the usual starting figures by garment.
Labour: Piece Rate or Time
If your karigars are on piece rate, the labour line is simple: the rate per garment, plus cutting, plus checking and pressing if those are paid separately.
If they are on a daily wage, work out the output first. A team of four that produces 80 kurtis a day at a combined wage of Rs 3,200 costs Rs 40 a piece in stitching labour. If a new style slows them to 60 a day, the same wage is Rs 53 a piece. That difference belongs on the sheet before the quote, not in the accounts after it.
For a new style, stitch a sample and time it. A sample that takes far longer than expected is the cheapest warning you will ever get.
Do not forget the people who do not stitch. The cutter, the helper who trims threads, the checker and the man at the ironing table are all paid whether or not their work appears on a piece-rate card. Add their wages for the order and divide by the pieces, or the labour line will always look cheaper than the labour really was.
Overheads and Rejections
Overheads are the costs that do not change with the order: rent, electricity, the supervisor's salary, machine repairs, loan instalments. Add them up for a month and divide by the number of pieces you normally produce in a month. That gives you an overhead per piece to put on every costing sheet.
Rejections are the pieces that are cut and stitched but cannot be sold: stains, wrong measurements, fabric faults found late. Look at your last few orders and count how many pieces failed checking. If one piece in forty failed, every good piece has to carry the cost of a fortieth of a bad one. Our guide to managing garment production covers how to track rejections stage by stage so the number on your sheet is real.
Keep the Sheet After the Order
The costing sheet is a prediction. When the order is finished, fill in a second column with what actually happened: real fabric used, real output per day, real rejections. The difference between the two columns is the most useful information a small unit can have.
After three or four orders, your predictions get much closer, because the sheet has learned your unit. You also see which buyers' styles always cost more than expected, and which ones are worth taking again. Units that do job work or their own production need this second column most, because the margin on job work is thin enough that one bad estimate wipes it out.
Frequently Asked Questions
What is a garment costing sheet?
A one-page calculation for each style that lists every cost per finished piece, fabric, trims, thread, labels, labour, finishing, overheads and rejections, before the price is quoted.
How do you calculate fabric consumption per garment?
Lay out a full size set of pattern pieces on the actual fabric width, as tightly as possible, measure the length used and divide by the number of pieces. Then add shrinkage and wastage allowances.
How do you include overheads in garment costing?
Add up the fixed costs for a month, such as rent, power and salaries, and divide by the number of pieces you normally produce in a month. Add that amount to every piece.
Why should rejections be part of the costing?
Because every rejected piece used fabric and labour that has to be paid for by the pieces you do sell. If one piece in forty is rejected, each good piece carries a fortieth of the cost of a bad one.
Where Juvee Helps
A costing sheet is only as good as the figures behind it: fabric issued and returned, output per day, pieces rejected at each stage. Juvee records all three as the order moves through the unit, so the second column of the sheet fills itself; see garment manufacturing software. The Basic plan is free with no time limit, and paid plans start at ₹10,190 a year including GST; the pricing page lists every plan.